Fish Lake Interchange

Improving One of the I-94 Corridor’s Most Critical Connections

The I-94 Fish Lake Interchange, located within the City of Maple Grove, is a system-to-system interchange within the Twin Cities Metro regional highway network that is critical to mobility and commerce within the region, state and Upper Midwest.

A long-known deficiency of this interchange’s configuration involves a four- to three-lane center merge in the westbound direction, which creates congestion and safety issues. Safety concerns and congestion also exist on western I-94 / I-694 and southern I-494 legs of the system interchange.

In 2020, the Metropolitan Council partnered with MnDOT to produce the Freeway System Interchange Study, which studied 56 Twin Cities freeway-to-freeway interchange locations. The Fish Lake Interchange was identified as one of 17 locations where further planning effort was merited, and 11 initial solution concepts were identified.

The Challenge

Traffic converging at the Fish Lake Interchange creates recurring congestion and operational challenges, particularly where westbound I-94 and northbound I-494 traffic merge.

Previous regional analysis identified the interchange as an area in need of improvement, including the existing four-lane-to-three-lane merge between westbound I-94 and northbound I-494.

For communities along the I-94 corridor, this is more than a traffic issue. The interchange is a gateway between the Twin Cities and the rapidly growing communities and employment centers northwest of the metro. Congestion here affects commuters, freight movement, businesses and access throughout the corridor.

Our Goal

The Coalition's goal is to advance a practical, fundable improvement to the Fish Lake Interchange that can provide meaningful congestion relief in the near term while fitting within a broader long-term vision for the interchange.

Working with our transportation partners, we are advocating for a project that will:

Where the Project Stands

Funded through Corridors of Commerce Readiness Advancement, the I-94 Fish Lake Interchange Study will determine possible long-term concepts for the interchange and help select an agency-supported near-term alternative that could advance through federal and state funding.

The study will consist of four phases:

  • Phase 1: Background and Context and Existing and Future Conditions.
  • Phase 2: Alternatives Evaluation: Identification, refinement and evaluation of long-term vision concepts and near-term alternatives.
  • Phase 3: Environmental Study: Federal and State
    environmental reviews of the near-term agency-
    supported alternative.
  • Phase 4: Preliminary Design to produce a signed layout of the Preferred Alternative.

Project Status

Planning

In Progress

Near-Term Alternative

In Development

Environmental Review

Future Phase

Design

Future Phase

Construction Funding

To Be Secured

Construction

To Be Determined

Study Schedule and Next Steps

Study Schedule

  • Study RFP issues – July 7, 2026
  • RFP due date – August 11, 2026
  • Anticipated award – September, 2026
  • Phases 1 & 2 completion – 12 to 18 months
  • Phases 3 & 4 completion – December 30, 2028 (earliest date)

Next Steps:

  • Corridors of Commerce Capital Construction Solicitation (funding application for near-term agency-supported alternative) – Fall 2027
  • Pursue state and federal funding programs:
    • Freight-related funding opportunities
    • Safety program funding
    • Discretionary federal grants

Why It Matters

Less Congestion

Address one of the most significant traffic bottlenecks along the I-94 West corridor and improve the daily commute for thousands of motorists.

Safer, More Reliable Travel

Improve traffic operations where three major interstate corridors converge, reducing conflicts and creating more predictable travel.

Stronger Freight Connections

Keep goods moving efficiently between the Twin Cities, northwest Minnesota and destinations beyond.

Supporting a Growing Corridor

Ensure transportation infrastructure keeps pace with continued residential, commercial and employment growth throughout the I-94 West corridor.